Question

The following costs have been estimated for the activities in a project:

A.Develop a cost budgeted scheduled based on the earliest start time. Keep once decimal place

B. Develop a cost budgeted schedule based on the latest start time. Keep one decimal place

Please show all work and do not hand write. Thanks

Activity

Immediate Predecessors

Time

Total Cost($)

A

9

10800

B

5

8500

C

A

4

6400

D

B

6

13620

E

C,D

11

9240

F

C,D

5

14000

G

F

8

7600

 